Validation of bundled small-scale projects
Validation of bundled projects may take place at the same time:
Several small-scale CDM project activities may be bundled for the purpose of validation (4/CMP.1, Annex II, paragraph 19).
The rule that a single DOE may perform validation as well as verification and certification for small-scale projects applies equally to bundled projects:
A single designated operational entity may perform validation as well as verification and certification for a small-scale CDM project activity or bundled small-scale CDM project activities (4/CMP.1, Annex II, paragraph 20).