Relevant rules/decisions
5/CMP.1, Annex, paragraph 37 states the modalities and procedures for issuance of CERs also apply to issuance of tCERs and lCERs from afforestation and reforestation CDM project activities
5/CMP.1, Annex, paragraph 36 describes how requests for issuance in relation to A/R project activities are dealt with.
The Procedures for review of a proposed issuance of CERs in accordance with 3/CMP.1, Annex, paragraph 65 are set out in 4/CMP.1, Annex IV and have been clarified by the Executive Board in EB 15 Annex 12; EB 15 Annex 13 (Report to COP, Annex 1); EB 25 paragraph 106; EB 25 Annex 48; EB 27 paragraph 66; EB 27 Annex 16; EB 28 paragraph 93; EB 28 Annex 42; EB 29 paragraph 81; EB 29 Annex 16; EB 32 paragraph 80.
The responsibility for costs of a review of a proposed issuance of CERs are set out in 4/CMP.1, Annex IV, paragraph 21 and have been clarified by the Executive Board in EB 15, Annex 12, paragraph 21.
The rule that the modalities and procedures for conducting a review of a proposed issuance of CERs apply to reviews in relation to tCERs and lCERs is set out in 5/CMP.1, Annex, paragraph 37.
